The houses have different colours which represent the different states that the Job can be in:


Grey

indicates that the Job has not had its Call Sheet downloaded yet.

Blue

indicates that new discussions have been downloaded

Brown 

indicates that the Job has not had its Scheduling Status marked complete. 

Green 

indicates that the Job has a Scheduling Status of complete. 

3 Grey Houses

indicates that the project job has not had its Call Sheet downloaded yet. 

3 Houses

indicate that the job is part of a project. When it is clicked, a pop menu gives the options of Call sheet, View Project Jobs and Common Call sheet. 

Green and grey

double ticks

indicate that the job has an outstanding inspection.



Job Downloaded but not Call Sheet

Grey House Status Icon indicates that the Job has not had its Call Sheet downloaded yet.



New Discussions/Messages on Job

Blue House Status Icon indicates that new discussions, messages against the job when added by some other user (example: Senior Supervisor or Admin Staff)



Scheduling status not Complete

Brown House Status Icon indicates that the Job has not had its Scheduling Status marked complete. Most active jobs will appear in this status as they are still being constructed.



Scheduling Complete

Green House Status Icon indicates that the Job has a Scheduling Status of complete.



Outstanding Inspection

Green and Grey double tick House Status Icons indicate that the job has an outstanding inspection.